Project Closeout

The practice of project closeout finalizes all project activities completed across all phases of the project to formally close the project and transfer the completed or cancelled project as appropriate.

The purpose of project closeout is to assess the project, ensure completion, and derive any lessons learned and best practices to be applied to future projects. However, in multi-phase projects, the close-out practice may be applied at various stages of the project; upon deliverable completion, upon phase completion, upon iteration completion, at designated times during the project’s life, or at whatever other juncture represents a completed segment of project work. Applying the close-out practice in this manner closes out only the portion of the project scope and associated activities applicable to that portion of the project.

The practice of project close-out consists of two main activity groups:

  • Administrative Closure
  • Contract Closure

Administrative Closure

The administrative closure process defines activities, interactions, and related roles and responsibilities of the project team members and other stakeholders involved in executing the administrative closure procedure for the projects.

Kitchen Exhaust Hood Testing and Balancing

Contract closure includes activities and interactions needed to settle and close any contract agreements established for the project, as well as those related to supporting the formal administrative closure of the project.

  • Confirming the project has met all sponsor, customer, and stakeholder requirements

  • Verifying that all deliverables have been delivered and accepted

  • Validating exit criteria have been met

Contract Closure

Contract closure includes activities and interactions needed to settle and close any contract agreements established for the project, as well as those related to supporting the formal administrative closure of the project.

Contract closure involves verification that all work has been completed correctly and satisfactorily, updating of contract records to reflect final results, and archiving information for future use. Among other activities contract closure includes:

  • Confirming the project has addressed the terms and conditions of the contracts

  • Confirming completion of exit criteria for contract closure

  • Formally closing out all contracts associated with the completed project

Project closeout should be anticipated and planned as early as possible in the project lifecycle even though it is often the last major process of a project’s life. At a high-level, the key elements of project closeout are:

  • Verify acceptance of final project deliverables

  • Conduct post-project assessment and lessons learned

  • Conduct post-project review and evaluation

  • Recognize and celebrate outstanding project work

  • Disburse project resources – staff, facilities and automated systems

  • Complete and archive final product records

  • Ensure transfer of knowledge

MORE DETAILS

SHARE ON SOCIAL MEDIA!

incoma commissioning tad cx devreye alma işletmeye alma incoma engineering & consultancy

+90 322 322 1122

+90 533 199 8373

info@incoma.com.tr

ADANA

Head Office

Dedekorkut Mah. Ilbey Gunes Cad. No:15  Kat:1 Yuregir, 01285

Adana / Turkey

FOLLOW US ON SOCIAL MEDIA

© Copyright 2013 - | Incoma Engineering & Consultancy LTD. | All Rights Reserved. | Design by Medya Fabrikası Creative Works